Paute Inflows Enter the Dry Season Below Historical Benchmarks
Energy

Paute Inflows Enter the Dry Season Below Historical Benchmarks

Chip MorenoChip Moreno||Source: Primicias

Ecuador's Paute Integral system enters the September 2026-March 2027 dry season with below-historical water inflows. Mazar averaged 56 m³/s in August 2026, versus a historical August average of 90 m³/s.

The wider Paute River basin averaged 94.8 m³/s in August, against a historical August average of 136.4 m³/s. The figures are the most useful operating signal in the current report: they describe the water input available to a generation system that supplies a large share of Ecuador's average demand.

Operating data

IndicatorCurrent / reference
Paute basin, August 202694.8 m³/s
Paute basin historical August average136.4 m³/s
Mazar, August 202656 m³/s
Mazar historical August average90 m³/s
Mazar historical September average68 m³/s
Mazar level at 17:00 on September 12,147.2 msnm
Mazar maximum / critical level2,153 / 2,115 msnm

The Ministry of Energy confirmed that Ecuador's dry season begins in September 2026 and could extend through March 2027. The operating problem is mechanical: lower river flows reduce hydroelectric generation. The report also says El Niño is expected during the dry-season window and could reduce flows further, while noting that weather remains difficult to predict.

The generation concentration

Paute Integral is a cascade of three facilities: Mazar at 170 MW, Paute-Molino at 1,100 MW, and Sopladora at 487 MW. Together, they represent about 3,350 MW, equal to nearly 76% of Ecuador's average demand in August 2026.

Mazar has the lowest installed capacity in the cascade but the reservoir function that supports the other plants. Its maximum level is 2,153 meters above sea level and the critical level is 2,115 meters. At 17:00 on September 1, 2026, the reported level was 2,147.2 msnm.

The report notes that when Mazar has reached 2,115 msnm in previous situations, the complex has left operation and Ecuador has recorded power cuts, including in 2024. This is a historical operating reference, not an announcement of a current blackout schedule.

The comparison set extends beyond Paute. Agoyán averaged 38.3 m³/s in August 2025 and 20 m³/s in August 2026. Coca Codo Sinclair, which operates without a Mazar-style reservoir, averaged 367 m³/s in August 2026, above its historical August average of 330 m³/s but below its August 2025 average of 414 m³/s.

Import and price transmission

The report identifies electricity purchases from Colombia as one way to preserve water in Mazar. It also says there is a high probability of higher electricity prices between November and December 2026, because Colombia anticipates more drought in that period as El Niño develops.

For businesses, this creates a monitoring chain rather than a single forecast: reservoir levels, inflow data, Colombia's supply and price, and the timing of any official operating measures. The current report does not identify a final import contract or announce future rationing.

What to watch

  • Mazar's distance from the 2,115 msnm critical level.
  • September inflows against the 68 m³/s historical September benchmark.
  • Official information on Colombia electricity purchases and price formation.
  • Whether the Paute system's 3,350 MW of capacity remains available through the dry-season window.

Source: Primicias

Source

Primicias — "Caudales del complejo hidroeléctrico Paute, el más grande del país, estuvieron por debajo del promedio histórico en agosto"

View original
Paute IntegralMazarhydroelectricelectricityEl Nino
Companies: Ministerio de Energía, Celec
Regions: Azuay, Cañar, Ecuador
Share
Research Support

Support daily Ecuador business intelligence.

Research support funds source monitoring, data checks, editing, publishing, and sector coverage for professionals tracking Ecuador.

Daily Briefing

Ecuador business intelligence, delivered at 6 AM ECT.

Related Coverage

Energy

Petroecuador's August Output Missed Target Despite an 8% Year-to-Date Gain

Petroecuador averaged 365,704 barrels per day in August, below its 370,000-barrel projection. January-August output was 8% above the same 2025 period, but the comparison is distorted by the July 2025 collapse and remains below earlier benchmarks.

Primicias|
Energy

Villonaco III Advances With 112.1 MW Capacity and USD 200M-Plus Private Investment

Villonaco III has received 30 of 57 wind-turbine blades for a planned 112.1 MW project between Loja and Catamayo. The concession carries more than USD 200 million in private investment, a 25-year term, and a third-quarter 2027 commercial-operation target.

El Universo|
Energy

Ecuador’s USD 42.7M Barge Renewal Suspension Is an Execution Signal

Sercop suspended a six-month renewal process for one Karpowership barge in Guayaquil, leaving a 90-110 MW procurement question open ahead of the dry season.

Ecuavisa|
Energy

Energy Supply Brief: 270 MW Offline at Minas San Francisco, Karpowership Barge Renewal Stalled, New Minister's Corporate Ties Under Scrutiny

Ecuador's electricity supply margin tightened further this week as the 270 MW Minas San Francisco plant went offline for mandatory reservoir maintenance through May 16, while the Karpowership Emre Bey barge's contract renewal remains suspended by Sercop procurement objections. Meanwhile, new Energy Minister Juan Carlos Blum's shareholdings in a state-contracting consultancy raise governance questions.

Primicias|
Energy

Celec's Sopladora Plant Returns to Full 487 MW Capacity — Three Units Online Since April 5

Ecuador's Sopladora hydroelectric plant — operated by Celec Sur — returned to full installed capacity of 487 MW on April 5, 2026, completing replacement of a 40-tonne turbine shaft on Unit 2 damaged in a July 2023 technical event. The facility had operated at ~80% capacity from April 2024 until shaft replacement. Paute Integral complex (of which Sopladora is part) supplies roughly 40% of national demand.

Expreso, Teleamazonas|
Opens WhatsApp with a pre-filled message