CELEC Has No Awards Across 205 MW Emergency Thermal Rental Pipeline
Energy

CELEC Has No Awards Across 205 MW Emergency Thermal Rental Pipeline

Chip MorenoChip Moreno||Source: Primicias

CELEC's emergency thermal rental pipeline is not converting into awarded capacity.

Procurement Status

Primicias reports that Corporacion Electrica del Ecuador (CELEC) planned to contract 205 MW in rented thermal generation to mitigate the risk of power cuts in 2026. As of May 22, 2026, none of the recent processes had reached award.

ProjectCapacityStatus reported by Primicias
Pascuales50 MWDeclared deserted, then relaunched
Jaramijo15 MWDeclared deserted on May 6
Miraflores25 MWDeclared deserted on May 20
Santa Elena45 MWDelayed; should already have been awarded
Guangopolo10 MWDelayed; should already have been awarded by May 18
Salitral60 MWNot yet launched in Sercop

Primicias reports that the Jaramijo process received 19 offers, but all were disqualified for not meeting minimum requirements. Miraflores received seven offers, with the same result.

Process Risks

According to Primicias, the failed Jaramijo and Miraflores processes had common issues. Sercop observations flagged proformas submitted without proper electronic signatures or responsibility signatures, and some providers did not detail execution-stage timelines.

The report also says most disqualifications were tied to bid seriousness guarantees, supplier-registration eligibility, or experience being credited as construction or supply rather than rental-service experience.

CELEC has relaunched only the Pascuales 50 MW process so far. Primicias reports that the relaunched process has a budget of $77.1 million and is scheduled for award by Friday, May 29.

Business Implications

IssueSignal
Capacity gapThe 205 MW emergency rental package has not become contracted supply.
Procurement executionTechnical eligibility and document-compliance issues are preventing awards.
Supplier opportunityPascuales remains active, but other packages require procedural recovery.
Grid riskDelays reduce the buffer available before dry-season stress.

What to watch

  • Whether Pascuales is awarded by May 29.
  • Relaunch decisions for Jaramijo and Miraflores.
  • Progress on delayed Santa Elena and Guangopolo files.
  • Whether Salitral's 60 MW process enters Sercop.

Source: Primicias

Source

Primicias — "Ecuador: Celec no logra adjudicar contratos de generación termoeléctrica para mitigar el riesgo de cortes de luz en 2026"

View original
CELECthermal generationSercoppower supply
Companies: CELEC, Sercop
Regions: Ecuador, Pascuales, Jaramijo, Miraflores, Santa Elena, Guangopolo, Salitral
Share
Research Support

Support daily Ecuador business intelligence.

Research support funds source monitoring, data checks, editing, publishing, and sector coverage for professionals tracking Ecuador.

Daily Briefing

Ecuador business intelligence, delivered at 6 AM ECT.

Related Coverage

Energy

Ecuador Implements Energy Measures Amid El Niño Threat and Long-Term Sustainability Goals

Ecuador's Ministry of Environment and Energy is coordinating with industries to manage energy supply during the El Niño phenomenon. High-voltage consumers are asked to voluntarily disconnect one day a week, while the government also plans to contract additional electricity generation barcazas.

eluniverso.com; vistazo.com; vistazo.com|
Energy

Ecuador Updates Permit for $277.7 Million Peru Power Interconnector

Ecuador’s environmental-license update advances the Peru interconnection project. The next test is construction and commissioning against the stated 2029 target.

Primicias; Vistazo|
Energy

ITT Equipment Failure Cut Output to About 15,000 Barrels a Day

An ITT processing-system failure interrupted production beginning September 6. The latest cited operating data precede today, so full restoration remains unverified.

Primicias|
Energy

Progen Investigation Expands to 30 People as Ecuador Reopens Power-Contract Questions

Ecuador’s Fiscalía is seeking to add nine people to the Progen case, bringing the total number of investigated individuals to 30. The investigation concerns contracts for thermal generators and a reported potential loss above USD 100 million.

Primicias|
Energy

Ecuador Secures USD 3.5M To Prepare Strategic Electricity Projects

The grant includes detailed engineering studies for the San Gregorio–Palestina transmission line in El Oro and Guayas, with the program designed to strengthen Ecuador’s National Transmission System.

Primicias|
Opens WhatsApp with a pre-filled message